STRUCTURA ACADEMIC · LESSON AREA

Integrated Performance and Earned Value

Integrated performance and earned value · Construction Planning, Scheduling and Project Control

Course review
StandardInternational undergraduate curriculum synthesis with construction-management education, earned-value teaching and schedule-quality practice sources; project control-account, accounting and forecasting rules require local verification
Source3 source files
Review stateTechnical and publication gates pending
LEARNING OUTCOMES

After this chapter, you should be able to

  • Explain the scope, budget and status-date conditions required for integrated performance measurement.
  • Calculate planned value, earned value and actual cost for a bounded control account.
  • Calculate and interpret schedule and cost variances and performance indices.
  • Distinguish cost-based schedule signals from critical-path and milestone analysis.
  • Compare cost-efficiency, combined-efficiency and bottom-up estimates at completion.
  • Diagnose data, scope, production, price and cut-off causes that can produce similar indicators.
  • Write a control narrative linking numerical signal, confidence, forecast consequence, action, owner and review trigger.

The decision: what do the schedule and cost signals mean together?Source §Integrated performance · Decision-led opening

A control account can appear late, over cost, both or neither depending on the compatible scope, status date and value basis. Earned value creates disciplined comparisons, but the ratios remain signals. Management still needs production, network, risk and accounting evidence to explain cause and choose action.

Prerequisite checkSource §Learning sequence · Prior knowledge

Integrated control requires defined scope, an authorised time-phased budget, objective progress and actual cost under compatible cut-offs. If those foundations differ, correct the data basis before calculating ratios.

Compatibility gates before calculation
GateQuestion
ScopeDo plan, achievement and cost describe the same authorised work?
TimeDo schedule and accounting records use compatible status and cut-off dates?
BudgetIs the budget authorised, time-phased and mapped to the control account?
ProgressIs achievement measured objectively under a declared rule?
Actual costAre incurred cost, accruals and exclusions stated consistently?
SELF CHECK

Reject an incompatible comparison

Earned value uses accepted work to Friday, while actual cost excludes the final two reporting days. What is required before interpreting the cost index?

  • Calculate anyway
  • Align or explain the accounting cut-off and scope
  • Replace actual cost with planned value
Reveal answer and feedbackAlign or explain the accounting cut-off and scope

The cost index is meaningful only when earned work and incurred cost are comparable under the stated cut-off.

Connect scope, time-phased budget and verified achievementSource §Integrated control model · Integration concept

Earned value assigns authorised budget value to defined scope, places that value in time and earns it only when the progress rule confirms achievement. Actual cost is then reconciled for the same work. The method integrates reference values; it does not replace field observation or the schedule network.

Original integrated-control model. Scope, time-phased budget, objective progress and actual cost converge at one control account and status date before indicators are calculated.Original STRUCTURA review diagram · technical sign-off pending
Budget at completion
The authorised total budget for the defined control-account scope.
Planned value
The authorised budget value of work scheduled by the status date.
Earned value
The authorised budget value of work objectively achieved by the status date.
Actual cost
The cost incurred for the achieved work under the stated accounting cut-off.
Estimate to complete
The current forecast cost required to finish the remaining authorised scope.
Estimate at completion
The current forecast total final cost for the defined scope.
Core value calculations
MeasureTeaching relationMeaning
Planned valueBudget at completion × planned progressBudgeted value scheduled by the cut-off
Earned valueBudget at completion × verified progressBudgeted value objectively achieved
Actual costRecorded cost under the accounting cut-offCost incurred for the compared scope
Planned value
PV = BAC × pp

BAC is budget at completion and p_p is the planned-progress fraction at the status date.

Earned value
EV = BAC × pv

p_v is the objectively verified-progress fraction for the same authorised scope and status date.

SELF CHECK

Define earned value

Which statement describes earned value?

  • Actual cash paid
  • Authorised budget value of objectively achieved work
  • Forecast final cost
Reveal answer and feedbackAuthorised budget value of objectively achieved work

Earned value values achieved scope at the authorised budget basis so it can be compared with plan and actual cost.

Compare planned value, earned value and actual costSource §Integrated control model · Three-value comparison

Planned value provides the time-phased reference, earned value reports budgeted achievement and actual cost reports incurred cost. Comparing earned value with planned value produces a schedule signal in cost units; comparing earned value with actual cost produces a cost signal.

Original pseudo-three-dimensional value comparison. Planned value, earned value and actual cost are shown as separate bars under one budget, scope and status-date basis.Original STRUCTURA review diagram · technical sign-off pending
WORKED EXAMPLE

Calculate the base control-account values

A control account has an authorised budget of one thousand cost units. By the status date, sixty percent was planned, forty-eight percent is verified and actual cost is five hundred sixty.

  1. Planned value

    1,000 × 0.60 = 600

    Planned value is six hundred
  2. Earned value

    1,000 × 0.48 = 480

    Earned value is four hundred eighty
  3. Actual cost

    AC = 560

    Actual cost is five hundred sixty
  4. Scope and cut-off check

    One control account and one status basis

    The three values are comparable in the teaching case

Result. Earned value is below both planned value and actual cost. Variances and indices quantify those two comparisons next.

Base control-account comparison
MeasureValueInitial signal
Planned value600Budgeted work scheduled
Earned value480Budgeted work achieved
Actual cost560Cost incurred
Earned minus planned−120Behind in budgeted-value terms
Earned minus actual−80Unfavourable cost signal
SELF CHECK

Choose the cost comparison

Which values are compared to assess the cost signal?

  • Earned value and actual cost
  • Planned value and budget at completion
  • Actual cost and calendar days
Reveal answer and feedbackEarned value and actual cost

Earned value represents the budgeted value of achieved work; actual cost represents what that achieved work cost under the cut-off.

Calculate variances and performance indicesSource §Integrated control model · Variance and indices

Variances retain the value unit of the control account. Indices express proportional performance. A negative schedule variance or index below one indicates less budgeted work achieved than planned; a negative cost variance or cost index below one indicates actual cost exceeds the budgeted value of achieved work.

Original variance-and-index map. Earned value is the common numerator or reference point, separating the schedule comparison with planned value from the cost comparison with actual cost.Original STRUCTURA review diagram · technical sign-off pending
Variance and index relations
MeasureRelationBase result
Schedule varianceSV = EV − PV480 − 600 = −120
Cost varianceCV = EV − AC480 − 560 = −80
Schedule performance indexSPI = EV / PV480 / 600 = 0.80
Cost performance indexCPI = EV / AC480 / 560 = 0.86
Schedule performance index
SPI = EV / PV

SPI compares budgeted achievement with budgeted work planned at the status date. It is not a fraction of project time or a direct measure of days early or late.

Cost performance index
CPI = EV / AC

CPI compares budgeted value achieved with actual cost incurred. Confirm accruals, scope and cut-off before interpretation.

WORKED EXAMPLE

Interpret the base indices

Use planned value six hundred, earned value four hundred eighty and actual cost five hundred sixty.

  1. Schedule variance

    480 − 600 = −120

    Unfavourable schedule signal in cost units
  2. Schedule index

    480 / 600 = 0.80

    Eighty cents of budgeted work achieved per planned budget unit at the cut-off
  3. Cost variance

    480 − 560 = −80

    Unfavourable cost signal
  4. Cost index

    480 / 560 = 0.857...

    Approximately 0.86 budget units earned per actual cost unit

Result. Both indices are below one, producing a behind-and-over signal. The ratios do not identify the cause or completion path.

SELF CHECK

Interpret schedule performance

SPI is 0.80. Which conclusion is defensible?

  • The project is exactly twenty percent late in calendar time
  • Budgeted achievement is below budgeted work planned at the status date
  • The critical path is known
Reveal answer and feedbackBudgeted achievement is below budgeted work planned at the status date

SPI is a budget-value ratio. Calendar delay and criticality require schedule-network evidence.

Compare conditional completion-cost forecastsSource §Forecasting · Forecast methods

An estimate at completion combines actual cost to date with a view of remaining cost. Formula forecasts extend a stated performance assumption; a bottom-up forecast re-estimates the remaining work. The control team compares methods and selects one only after explaining which future conditions are expected to persist.

Original forecast-choice tree. Current cost efficiency, combined cost-and-schedule efficiency and a new bottom-up estimate lead to different completion forecasts and explicit assumptions.Original STRUCTURA review diagram · technical sign-off pending
Illustrative estimate-at-completion methods
MethodTeaching relationEmbedded assumption
Cost efficiency continuesEAC = BAC / CPICurrent cost efficiency applies to total budget scope
Bottom-upEAC = AC + ETCRemaining scope has been freshly estimated
Cost and schedule efficiency continueEAC = AC + (BAC − EV) / (CPI × SPI)Both current efficiencies influence remaining cost
Select project formulas only through the governing control procedure. These relations are teaching comparisons, not universal forecasts.
Simple cost-efficiency forecast
EACc = BAC / CPI

This relation assumes current cost efficiency continues. It is unsuitable when future method, scope, price or productivity differs materially without adjustment.

Bottom-up forecast
EACb = AC + ETC

ETC is a new estimate of the cost to complete remaining authorised scope. The method is useful when future conditions differ from historical efficiency or when detailed remaining estimates are available.

WORKED EXAMPLE

Compare two base-case forecasts

Budget at completion is one thousand, actual cost is five hundred sixty, CPI is approximately 0.857 and a fresh estimate to complete is six hundred.

  1. Cost-efficiency forecast

    1,000 / 0.857142... = 1,166.7

    Approximately one thousand one hundred sixty-seven cost units
  2. Bottom-up forecast

    560 + 600 = 1,160

    One thousand one hundred sixty cost units
  3. Difference

    1,166.7 − 1,160 = 6.7

    The two forecasts are close in this teaching case
  4. Decision

    Compare future method and estimate evidence

    Select the method whose assumption is supportable

Result. Numerical closeness does not remove the need to state the forecast basis. A different remaining estimate or efficiency could produce a material range.

SELF CHECK

Choose a bottom-up forecast

The remaining work will use a new method and the team has a detailed current estimate. Which forecast is most directly supportable?

  • Actual cost plus the new estimate to complete
  • Budget divided by the old CPI without review
  • Planned value plus actual cost
Reveal answer and feedbackActual cost plus the new estimate to complete

A bottom-up forecast can reflect changed future conditions when the remaining estimate is current and traceable.

Investigate causes behind similar indicatorsSource §Interpretation and action · Cause analysis

Quantity error, rework, low production, late information, scope movement, price change, procurement timing and accounting cut-off can produce similar indices. The team reconciles field evidence, schedule paths, budget mapping, change records and the cost ledger before recommending action.

Original indicator-to-action chain. Numerical signals lead through data reconciliation, cause evidence, schedule and cost forecast, authorised response and verification rather than directly to a traffic-light decision.Original STRUCTURA review diagram · technical sign-off pending
Possible causes and corroborating evidence
Observed signalPossible causeEvidence to reconcile
Low SPIAccepted quantity behind planProgress record, production rate and network path
Low CPIRework or poor productivityQuantity, labour, plant, defect and cost records
Low CPIPrice or accounting cut-off effectPurchase records, accruals and price basis
Mixed indicesWork advanced at high costSequence, overtime, resource and cost evidence
Sudden improvementScope or progress-rule changeChange control, budget remap and rule history
  • Name the control account, scope, status date and accounting cut-off.
  • State planned value, earned value, actual cost and data confidence.
  • Report both variances and indices without converting SPI into days.
  • Identify the leading evidence-supported cause and alternative explanation.
  • Reconcile the current network path and completion milestone.
  • State the selected completion-cost forecast and embedded assumption.
  • Name the action, owner, authority, due date and verification trigger.
SELF CHECK

Move from signal to cause

CPI is below one. What should the team do before recommending recovery?

  • Assume labour productivity is the cause
  • Reconcile scope, quantities, rework, prices, accruals and cut-off evidence
  • Ignore actual cost
Reveal answer and feedbackReconcile scope, quantities, rework, prices, accruals and cut-off evidence

The same cost signal can have different causes and therefore different responses.

Explore one integrated control accountSource §Interactive learning · Simulation sequence

The explorer begins with the verified one-thousand-unit teaching benchmark. Predict the combined signal, vary planned and verified progress or actual cost, compare three completion forecasts and explain which schedule conclusion still requires critical-path analysis.

IMPLEMENTED REVIEW SIMULATION

Integrated Performance and Earned Value Explorer

Test how compatible scope, progress, actual cost and forecast assumptions alter value comparisons, indices and conditional completion-cost forecasts.

Learning sequence
Review the base control account · Record a combined signal prediction · Change one progress or cost input · Calculate PV, EV and AC independently · Compare SPI and CPI · Select and explain a forecast method · Load the aligned case · Name the network evidence still required
Assumptions
One control account · One authorised budget · One status and accounting cut-off · Objective verified progress · No scope change or currency effect · Three illustrative forecast methods · No critical-path or probabilistic model
States
Base account · Changed input · Behind and over · Ahead and under · Mixed · Aligned · Forecast method changed · Prediction checked · Invalid input · Reset
Validation
Implemented against deterministic teaching cases; independent technical approval pending
INTERACTIVE EARNED-VALUE EXPLORER

Reconcile scope, time and cost signals before choosing a forecast

Predict first. Compare budgeted planned work, budgeted achieved work and actual cost, then state the assumption inside the forecast.

Teaching control account · technical approval pending
One control accountOne status dateCompatible scope cut-offObjective physical progressNo network criticality model
PREDICT

What combined signal will the indices show?

Control-account inputs
Forecast assumption
Schedule index0.80earned value ÷ planned value
Cost index0.86earned value ÷ actual cost
Selected completion forecast1,166.7cost units · conditional method
Variance at completion-166.7budget minus selected forecast

Base control account loaded. Predict the combined schedule and cost signal before checking.

Schedule variance -120Cost variance -80Status Behind and over the budgeted cost of achieved work
CONTROL INTERPRETATION

The account has achieved less budgeted work than planned and spent more than the budgeted value of that achievement. Investigate quantities, productivity, rework, information, prices, scope and cut-off before selecting action.

Control-account indicators and conditional forecasts
MeasureValueInterpretation
Planned value600Budgeted value of work planned by the status date
Earned value480Budgeted value of verified work achieved
Actual cost560Cost recorded under the stated accounting cut-off
Cost-efficiency forecast1,166.7Assumes current cost efficiency continues
Bottom-up forecast1,160Actual cost plus a new estimate of remaining work
Combined-efficiency forecast1,318.3Assumes both current cost and schedule efficiency influence remaining cost
Reflect before continuing

Which scope and cut-off evidence makes planned value, earned value and actual cost comparable? What network or field evidence is still needed before describing the completion-date consequence?

Issue a control narrative with the indicatorsSource §Management interpretation · Control communication

Minimum integrated-performance record
RecordRequired statement
BasisControl account, authorised budget, status date and accounting cut-off
AchievementProgress rule, verified scope, value and source
CostActual, accrual, exclusions, currency and ledger status
SignalPV, EV, AC, variances, indices and confidence
ScheduleCurrent path, milestone consequence and limitations of SPI
ForecastMethods compared, selected estimate, assumption and range
ResponseCause evidence, action, owner, authority and review trigger
SELF CHECK

Communicate an incomplete cut-off

Actual cost is missing a material accrual. How should the dashboard treat CPI?

  • Present it as final
  • Label it provisional and quantify or explain the missing-cost exposure
  • Replace actual cost with earned value
Reveal answer and feedbackLabel it provisional and quantify or explain the missing-cost exposure

Decision-makers need the current signal and its data limitation together.

Lesson synthesisSource §Learning sequence · Synthesis

Key points

  • Integrated performance requires compatible scope, authorised budget, status date, progress and actual-cost cut-off.
  • Planned value is budgeted work scheduled; earned value is budgeted work achieved; actual cost is incurred cost.
  • Schedule and cost variances compare earned value with planned value and actual cost respectively.
  • SPI and CPI are signals; SPI does not identify calendar delay or critical-path consequence.
  • Completion-cost forecasts embed assumptions that must be compared and explained.
  • Similar indicators can arise from different production, scope, price, rework or accounting causes.
  • A control narrative joins numerical signal with confidence, cause, forecast, action, owner and trigger.

Source references recorded by the supplied chapter

  • Chartered Institute of Building — Accreditation and Education Framework.
  • Royal Institution of Chartered Surveyors — Project Management sector pathway.
  • Deakin University — Construction Management curriculum overview.
  • Colorado State University — Construction Management undergraduate course descriptions and learning outcomes.
  • All India Council for Technical Education — Model Curriculum for Undergraduate Degree in Civil Engineering.
  • United States Government Accountability Office — Schedule Assessment Guide.